The project will be delivered - through a combination of 20 to 30 construction packages - in two major phases. Packages related to the initial phase will be bid to allow construction to begin as soon as the 2004 home football schedule is completed. The work associated with the first phase will include:

  • South end zone replacement
  • Remove of Klotz Tennis Courts (to be rebuilt in new location off Mormon Trek Boulevard)
  • South concourse work
  • Initial foundation and construction work for the future press box
  • Initial south plaza site work
  • Initial Lot 43 replacement and campus utility work

Work related to the first phase will be completed in order to host football games as scheduled for the 2005 football season. Any work that continues during the 2005 season will be scheduled so that no interruptions in game-day activities occur.

The second phase of the project will be bid prior to the 2005 season and construction work for this phase will begin as soon as the 2005 home football season is completed. The second phase work will include:

  • Demolition and reconstruction of the existing press box
  • West concourse renovation
  • East concourse renovation
  • Completion of Lot 43 replacement
  • Completion of south plaza construction and site work

The construction staging for the project will be limited to the area south of Kinnick Stadium (currently the Klotz Tennis Courts). Completion of Lot 43 replacement work will be tied to the completion of the press box.

For additional information about the renovation of historic Kinnick Stadium,
contact the appropriate staff member.

Credit Card America Needs Farmers Wrestling Clinic Jr. Hawk Club
Leerfield Iowa.edu Big Ten Big Ten Network Iowa Iowa City Shop