The Project Timeline and Major Milestones

Kinnick Stadium Renovation
Construction Packages
Celebration of 75 Years
We Thought You'd Enjoy This
March 2003
Permission to proceed approved by Board of Regents

June 2003
Architectural selection approved

July 2003
Architectural agreement approved and Board of Regents' capital project evaluation criteria received

September 2003
Ratification of executive director authorization to use services of construction manager and approval of construction manager selection

December 16, 2003
Program statement approval requested and acceptance of the master plan requested from the Board of Regents

December 2003-January 2004
Schematic design work - Phase 1 and Phase 2

January 2004-February 2004
Banking committee and Board of Regents review of financial plan

March 10, 2004
Schematic design and budget approved by the Board of Regents

March 2004
Design Development - Phase 1 and Phase 2

April 2004-June 2004
Construction documents - Phase 1

May 2004-August 2004
Site utility work

July 2004-August 2004
Bidding - Phase 1

September 2004-November 2004
Contractor mobilization and procurement - Phase 1

December 2004-August 2005
Demolition and construction - Phase 1

August 2004-December 2004
Construction documents - Phase 2

January 2005-February 2005
Bidding - Phase 2

March 2005-November 2005
Contractor mobilization and procurement - Phase 2

December 2005-August 2006
Demolition and construction - Phase 2

August 2006
Substantial completion

For additional information about the renovation of historic Kinnick Stadium,
contact the appropriate staff member.